structured cabling and clean power across 320 sites, from maputo to cabo delgado — 3,298 network points certified, delivered between 2022 and 2024.
the client needed to modernise the network and power infrastructure of its facilities across the country — from the maputo headquarters to provincial and district offices.
this was not a single-building project. it was 320 sites spread across 10 provinces, each with its own reality: ageing buildings, degraded electrical installations and critical equipment that could not stop during the works.
the project demanded full traceability: every site auditable, every material specified, every delivery certified and documented.
we split more than 20 technicians into dedicated teams advancing simultaneously across provinces — from maputo to cabo delgado.
dedicated teams per region, working simultaneously. the same methodology, the same quality standards — in maputo or in pemba.
weekly meetings with updated gantt charts, progress photos and an open-issues log. the client never had to ask "where are we?" — they always knew.
when the global materials crisis delayed deliveries, we re-sequenced sites and redeployed teams to keep the pace — without compromising the specification.
survey, decommissioning, trunking, cabling, boards and ups, testing, final inspection and handover. a standardised methodology means predictable quality.
every site received structured cabling and clean power — designed together, installed by the same team.
all 320 sites were inspected and certified before formal handover — with documentation that allows the client to operate and expand the network independently.